By BOB SHRALUKA
WZBD.com
Alley repairs are continuing in Decatur, with the project now having been doubled in size.
Street/Sanitation Superintendent Matt Schultz told the city’s board of works and safety at its Tuesday meeting that more favorable bids from Wayne Asphalt is allowing four more alleys to repaired.
The project started with three alleys on the repair list, but that number has now been enlarged to seven.

The alleys between Monroe and Jackson streets, and between Fourth and Fifth streets – 770 feet long in total – are on the new list.
As are the alleys between Indiana and Short streets and between Fifth and Sevenths, 758 feet in all.
The accepted bids are $22,650 for the former and $224,000 for the latter.
All milled material will be taken to the city’s pubic works site on Elm St.
The Fort Wayne company’s bid for the first three alleys was a little over $45,000.
The work has been ongoing and is likely to be completed next week, according to Schultz.