By BOB SHRALUKA
WZBD.com
If all goes as scheduled, milling of several Decatur streets will begin this week.
Operations Manager Jeremy Gilbert told city council at its latest meeting that Brooks Construction will begin the milling (removing the top layer of asphalt) “and it will be a long, drawn-out process.”
If the Brooks schedule holds, paving will begin on Sept. 17.
A state Community Crossings grant is funding the major portion of the project.
The grant totals $810,508.10. The city is providing a match of some $253,300 (which was budgeted), boosting total funds available for the work to over $1 million: $1,013,135.12.

The work includes resurfacing the Riverside Center parking lot and the city lot behind Two Brothers.
Following is the schedule released by Brooks:
9/5/2024: Along with pouring sidewalks on 5th Street, milling:
Edgewater
Waters Edge
Fremont Lane
Homestead Drive

9/6/2024: Along with pouring sidewalks on 5th Street, milling:
Elm
Alley off Elm
Grant Street Patch
Oak Street
7th Street
9/7/2024, milling:
Meibers Street
Start on Adams Street

9/9/2024:
Finish Adams Street
9/10/2024, milling:
4th Street
5th Street
9/11/2024: milling:
Finish 5th Street
2 Brothers Lot
9/12/2024: milling:
Mercer Ave patch
Riverside Center lot, Cleaning & Milling

Paving to begin on 9/17/2024, starting with the Mercer Ave surface patch, 2 Brothers parking lot. Then to move to Adams Street end of day.
9/18: Finish Adams & start 5th street
9/19: Finish 5th street
9/20: 7th Street & Meibers
9/21: 4th Street(no school) & Oak Street
9/23: Homestead, Elm, Alley off Elm, Grant St Patch
9/24: Waters edge, Fremont
9/25: Riverside Center lot
9/26: Approaches, misc. work